  • Water Mains - East Bank WV
    A water main construction project in East Bank, West Virginia was undertaken with the aid of federal Public Works Administration (PWA) funds. The PWA supplied a $10,600 loan and $3,968 grant toward the $14,568 eventual total cost of the project. Work occurred between Aug. and Oct. 1934. PWA Docket No. 2199
  • Disposal Plant - Peterstown WV
    A wastewater disposal plant construction project in Peterstown, West Virginia was undertaken with the aid of federal Public Works Administration (PWA) funds. The PWA supplied a $10,000 loan and $4,003 grant toward the $13,979 eventual total cost of the project. Work occurred between Dec. 1934 and Jun. 1935. The location and status of the facility are unknown to Living New Deal. PWA Docket No. 1925
  • Waterworks - Parsons WV
    A waterworks construction project in Parsons, West Virginia was undertaken with the aid of federal Public Works Administration (PWA) funds. The PWA supplied a $58,000 loan and $21,652 grant toward the $78,872 eventual total cost of the project. Work occurred between Jul. and Nov. 1934. PWA Docket No. 1737
  • Sewers - Point Pleasant WV
    A combination sewer construction project in Point Pleasant, West Virginia was undertaken with the aid of federal Public Works Administration (PWA) funds. The PWA supplied a $83,000 loan and $27,552 grant toward the $109,994 eventual total cost of the project. Work occurred between Aug. 1934 and Feb 1935. PWA Docket No. 1648
  • Waterworks - Ripley WV
    A waterworks construction project in Shinnston, West Virginia was undertaken with the aid of federal Public Works Administration (PWA) funds. The PWA supplied a $28,000 loan and $8,533 grant toward the $33,760 eventual total cost of the project. Work occurred between Dec. 1934 and Aug. 1935. PWA Docket No. 1356
  • Waterworks - New Cumberland WV
    A waterworks construction project in New Cumberland, West Virginia was undertaken with the aid of federal Public Works Administration (PWA) funds. The PWA supplied a $46,000 loan and $13,341 grant toward the $58,782 eventual total cost of the project. Work occurred between Nov. 1934 and May 1935. PWA Docket No. 1647
  • Waterworks - Danville WV
    A waterworks construction project in Danville, West Virginia was undertaken with the aid of federal Public Works Administration (PWA) funds. The PWA supplied a $18,860 loan and $7,279 grant toward the $26,224 eventual total cost of the project. Work occurred between Nov. 1934 and Feb. 1935. PWA Docket No. 1635
  • Waterworks - Summersville WV
    A waterworks construction project in Summersville, West Virginia was undertaken with the aid of federal Public Works Administration (PWA) funds. The PWA supplied a $25,100 loan and $6,946 grant toward the $31,918 eventual total cost of the project. Work occurred between Jun. and Nov. 1934. PWA Docket No. 1190
  • Waterworks - Fayetteville WV
    A waterworks construction project in Fayetteville, West Virginia was undertaken with the aid of federal Public Works Administration (PWA) funds. The PWA supplied a $51,700 loan and $15,301 grant toward the $67,159 eventual total cost of the project. Work occurred between Jun. and Nov. 1934. PWA Docket No. 1009
  • Waterworks - Shinnston WV
    A waterworks construction project in Shinnston, West Virginia was undertaken with the aid of federal Public Works Administration (PWA) funds. The PWA supplied a $35,700 loan and $13,341 grant toward the $50,381 eventual total cost of the project. Work occurred between Oct. 1934 and Jul. 1935. PWA Docket No. 899