  • Elementary School - Ripley MS
    Public Works Administration (PWA) project 1280 provided a grant of $16,411 for construction of a grammar school. Architect E. L. Malvaney designed the 1-story brick school. The Daily Clarion-Ledger reported both the high school and the elementary school were constructed with this grant. The project was approved 8/10/1938, construction started 11/21/1938, and the project was completed 10/28/1939 for a total of $35,074. WPA provided an additional $3,640 for the grammar school to add landscaping, playground equipment, and sidewalks in February 1940.
  • Williams Playground - Bangor ME
    A small park in Bangor with playground equipment, a basketball court and non functioning tennis court with plans to convert it into a Pickleball court. When constructed by the WPA as part of their comprehensive city-wide work program it originally contained a tennis court, concrete wading pool, playground area, baseball diamond and football field. According to various people who grew up in Bangor, the playground was a very important part of their lives and memories. "We always called it Newberry St. Park. Had a lot of fun there." "My Dad's family, the Burke's lived on Gridley St. and he (Bobby Burke)...
  • Union County Jail - New Albany MS
    A new county jail and improvements to the existing county courthouse were approved as PWA project 1272 July 23, 1938. E. L. Malvaney was architect for the two-story concrete Art Deco jail. Construction began 10/10/1938 and was completed 3/29/1939. PWA supplied a grant of $20,454 toward total cost of $45,577. Bonds were issued in the amount of $25,000 to contribute toward the cost of new jail construction and repair of the courthouse.
  • Street Improvements - New Albany MS
    New Albany received a grant of $28,800 to improve streets 9/13/1938 as PWA project 1324. Construction began 11/17/1938 toward the $62,195 project, completed 8/21/1939.
  • Catchings Consolidated School Additions - Delta City MS
    A new auditorium/gymnasium was added to the existing Catchings school as PWA project 1288. Architects Hull & Drummond designed the alterations and additions. A $9,000 loan and a $9,163 grant were provided. Approval was received 9/13/1938, and construction began 12/8/1938. The additions were completed 11/2/1939 for a total of $20,386. The name of the town was changed to Delta City sometime during the late 1940s.
  • Street Improvements - Shelby MS
    PWA Project 1343 for street improvement in Shelby was approved 9/16/1938 for a grant of $20,454. Contracts were awarded 11/30/1938 and construction began 12/5/1938. Work was completed 3/22/1939 for a total cost of $47,638. Mississippi House Bill 23 authorized the town of Shelby to borrow funds to contribute to the PWA funds.
  • Consolidated School - Holly Bluff MS
    Architect Edgar Lucian Malvaney designed the Holly Bluff school building, constructed in 1939 as PWA project 1271. It was approved 7/27/1938 and construction began 10/17/1938. It was completed10/12/1939 for a total cost of $57,305 with PWA funding a grant of $25,515. Bonds were issued in the amount of $25,000 for the remainder. Perry Construction Company built the new school, Paine Heating and Tile Company provided heating and plumbing, and Fatheree Electric Company completed the wiring. The building was dedicated and opened to the public October 7, 1939 and final inspection was made later that month by the architect, school supervisors,...
  • Jefferson County Courthouse - Mt. Vernon IL
    The Jefferson County courthouse in Mt. Vernon IL was built with funds from the Public Works Administration (PWA) in 1939.  It is a three-story concrete structure in Moderne or Art Deco style, designed by architect William R. McCoy, who was quite active in central Illinois at the time.  It is one of six New Deal county courthouses in Illinois (Weiser 2009).  Unfortunately, Weiser, Wikipedia and other sources make the common mistake of confusing the PWA with the Works Progress Administration (WPA). The courthouse is an elegant building, with a protruding south portico with  three vertical sections divided by bas-relief pillars.   Above...
  • Calhoun School - Laurel MS
    The Calhoun school was constructed 1939 as project x1289. A PWA grant of $13,622 was approved 9/13/1938. Construction began 12/16/1938 and was completed 7/13/1939 at a cost of $28,909. Architects were Landry & Matthes. The school was demolished in 2007.
  • Pascagoula High School (former) - Pascagoula MS
    PWA project W1263 was initiated February 1937 and approved for a loan of $100,000 and grant of $81,818 August 12, 1937. Bids were advertised November 6, 1937 and construction begun December 20. The Art Moderne style building was designed by the Mississippi architectural firm of Smith & Olschner and constructed by Newton & Schmoll. "At the time of its completion, the new school building was one of the most modern in the state since it incorporated state of the art equipment which reflected the latest ideas in school planning. Among the amenities included were a large library, a cafeteria, a...