Description
By building abutments and retaining walls, access was made possible to properties hereto inaccessible due to precipitous slopes of the hill. this work was of a precarious nature and required skill and courage. The photographs show the little homes on the edge of the slope. Ordinarily this work would be done by a contractor specializing in underpinning and foundation work.–Healy, p. 49.
Source notes
Healy, Clyde E. San Francisco Improved: Report of Clyde E. Healy, Assistant City Engineer - City of San Francisco and Coordinator of W.P.A. Projects, Period October 10, 1935 to August 31, 1939. San Francisco : [s.n.]., 1939.Contribute to this Site