- City:
- St. George, UT
- Site Type:
- Infrastructure and Utilities, Water Supply
- New Deal Agencies:
- Public Works Funding, Public Works Administration (PWA)
- Started:
- 1936
- Completed:
- 1937
Description
A waterworks construction project in St. George, Utah was undertaken with the aid of federal Public Works Administration (PWA) funds. The PWA supplied a $101,500 loan and $41,300 grant toward the $152,499 total cost of the project. Work occurred between January 1936 and July 1937.
(PWA Docket No. UT 1578)
Source notes
National Archives: Record Group 135: Public Works Administration; Projects Control Division; Entry 52: Indices to Non-Federal Projects; Report No. 5: Status of All Completed Non-Federal Allotted Projects, page 209.Site originally submitted by Evan Kalish on November 3, 2014.