Project type: Water Supply, Infrastructure and Utilities
Started: 1937
Completed: 1937
View Project in a Separate Window
Description
The federal Works Progress Administration (W.P.A.) furnished the cost of labor for the cleaning of the two reservoirs for the Town of Hatfield: the Mountain Street and Running Gutter Reservoirs.
Town Report: “With the help of WPA funds, we have done some work at the [Mountain Street] reservoir this summer. The small [Running Gutter] reservoir can be cleaned in one day, with two men; while it took fifteen men there for two weeks.”
Source notes
Hatfield Annual Town Report, 1937 https://archive.org/details/hatfieldannua19361944hatf https://www.townofhatfield.org/Pages/HatfieldMA_Bcomm/Open/ReservoirLoopTrail.pdf
Project originally submitted by Evan Kalish on June 7, 2016.
We welcome contributions of additional information on any New Deal project site.