- City:
- Flomaton, AL
- Site Type:
- Infrastructure and Utilities, Sidewalks and Stairs
- New Deal Agencies:
- Works Progress Administration (WPA), Work Relief Programs
- Completed:
- 1939
- Quality of Information:
- Very Good
- Site Survival:
- Extant
Description
The Works Progress Administration (WPA) built seven miles of sidewalks throughout the City of Flomaton. This work was part of a city-wide, streets and sidewalks construction program. The approximate cost of the entire program was $27,200.00. Pictured are WPA crews carrying out paving work on Palafox Street in Flomaton. The work consisted of blacktopping a three-mile stretch.
Source notes
Site originally submitted by Brent McKee on November 30, 2017.
Contribute to this Site
We welcome contributions of additional information on any New Deal site.
Submit More Information or Photographs for this New Deal Site