• Municipal Roadwork - Stony Brook NY
    According to Medford, New York's Mid-Island Mail, a Works Progress Administration (WPA) project in Stony Brook, New York, consisted of the construction of "9,000 lineal feet of sidewalk, 300 lineal feet of curb and gutter, 650 lineal feet of retaining wall and three catch basins ... on Erland road and Cedar street, Christian avenue and Main street" at a cost of $20,300.