    1936 Town Paid W.P.A. Account 13 employed $696.74 W.P.A. Paid Labor 16 employed $2,257.20 P. W. A. PROJECT NO. 1028R Pursuant to the vote taken by the town the Federal Project No. 1028R was completed. The water main extension was finished and service started in May 1936. The electric line extension to Long Pond was finished and service started July 3, 1936. The total estimated cost of project as approved by the P.W.A. Office was $6,360.00 the federal share to be 45% of the total actual cost. This project was completed at a cost of $5,139.28 in accordance with the rules and specifications of the Federal government, was audited...