• School Complex - Leakesville MS
    PWA w1104 funded the addition of a five-room building for high school classes and a new gymnasium on the Leakesville school complex. The award for loan of $12,500 and grant of $10,396 was approved 9/25/1935. Construction began 1/6/1936 and was completed 10/12/1936 for a total cost of $28,841. The classroom building was constructed by Oden and Glen for the sum of $11,441 and the remainder funded the gymnasium. The gymnasium also served as a community center in addition to athletic events. The new classroom building was added to the east end of the complex and the gymnasium to the west...