• School - Cascilla MS
    A one-story brick veneer school was completed as Public Works Administration project 3900, July 31, 1935. An $11,500 loan and a $5,371 grant were awarded on March 21, 1935. Construction began April 16, 1935. The total of the project came to $18,711 at completion. The school contained 6 classrooms, a music hall, an office, and a 46 x 90 feet auditorium. The project employed an average of 25 men per day with an average weekly payroll of $600. Contract was awarded to M. T. Reed Construction of Belzoni. W. G. Eckles, State Director of School Building Service was the architect.