• Hydro-electric Plant - Seward AK
    Public Works Administration project 6279 for an electric plant at Seward was approved 6/20/1934 for a $96,000 loan and a $30,000 grant. Construction finally began 8/6/1937 and was completed 8/7/1939 for a total cost of $136,170. The project proposed a dam and three-mile pipe line from Lost Creek to near the city and the construction of an electric plant "designed to supply practically unlimited power" (Seward will ask $148,000 PWA funds, Jan 9, 1935, p. 1). Stratton and Beers of Juneau placed the PWA bonds. Bennett and Taylor of Los Angles was awarded the contract for the construction of the...