Storm sewer under construction
Description
Works Progress Administration (W.P.A.) workers constructed a large storm sewer in Belmont, Massachusetts. From a W.P.A. Bulletin:
Sixty inch pipe is being laid on the Belmont WPA Wellington Brook Sewer Project. This storm sewer will run 510 feet from Waverl[e]y Town Yard to Waverl[e]y Street.
Source notes
Works Progress Bulletin, Massachusetts: July 31, 1936 (pg. 2) http://archive.org/details/worksprogressbul3637unit
Project originally submitted by Evan Kalish on January 10, 2017.