- City:
- Pawtucket, RI
- Site Type:
- Infrastructure and Utilities, Roads, Bridges, and Tunnels
- New Deal Agencies:
- Public Works Funding, Public Works Administration (PWA)
- Started:
- 1934
- Completed:
- 1935
Description
A street improvement project in Pawtucket, Rhode Island was undertaken with the assistance of federal Public Works Administration (PWA) funds. The PWA supplied a $31,000 loan and $11,463 grant for the project, whose total cost was $42,611; construction occurred between May 1934 and October 1935.
PWA Docket No. RI 3492.
Source notes
National Archives: Record Group 135: Public Works Administration; Projects Control Division; Entry 52: Indices to Non-Federal Projects; Report No. 5: Status of All Completed Non-Federal Allotted Projects, page 40.Site originally submitted by Evan Kalish on May 18, 2015.