PWA project 1200 for paving in Hernando was for $16,000 loan and $13,090 grant approved 11/17/1936. Construction began 4/5/1937 and was completed 6/10/1937 for a total cost of $29,571. The work included paving the street around the courthouse square and surfacing eight lateral streets in the town. Contract was awarded to Bowyer & Johnson for $25,037.

Source notes

Report No. 5, Status of Completed Non-Federal allotted projects. Region No. 3 Mississippi. (January 3, 1940). Federal Emergency Administration of Public Works Projects Division, p. 105.

Hernando plans street paving. (Mar 20, 1937). The Greenwood Commonwealth, p. 6.

Federal approval given 13 PWA projects in state. (Nov 24, 1936). Daily Clarion-Ledger, p. 14.

Project originally submitted by Susan Allen on November 4, 2019.

We welcome contributions of additional information on any New Deal project site.

SUBMIT MORE INFORMATION OR PHOTOGRAPHS FOR THIS SITE

Location Info


2535 US-51
Hernando, Mississippi 38632

Location notes: Streets around courthouse square include Hw. 51, Losher Street, Caffey Street, and W. Commerce Street.

Coordinates: 34.8230257, -89.9947444

Leave a Reply

Before leaving a comment, please note:

  • Comments allow viewers to share information with others or alert us to errors or changes in a New Deal site.
  • We are not involved in the management of New Deal sites and have no information about visits, hours or rentals.
  • This page shows all the information we have for this site; if you have new information or photos to share, click below.

SUBMIT MORE INFORMATION OR PHOTOGRAPHS FOR THIS SITE

We welcome contributions of additional information on any New Deal project site.

Your email address will not be published.