- City:
- Upper Lake, CA
- Site Type:
- Infrastructure and Utilities, Roads, Bridges, and Tunnels
- New Deal Agency:
- Unknown
- Started:
- 1934
Description
2.5 miles of highway was graded and surfaced near Clear Lake at a cost of $95,000 thanks to federal funds. Work began on this project during December 1934.
Source notes
Nov/Dec 1934 issue of California Highway & Public Works magazineSite originally submitted by Andrew Laverdiere on August 10, 2014.
Contribute to this Site
We welcome contributions of additional information on any New Deal site.
Submit More Information or Photographs for this New Deal Site
Join the Conversation