Project type: Electricity, Infrastructure and Utilities
Started: 1938
Completed: 1939
View Project in a Separate Window
Description
A power system-improvement construction project in Bryant, South Dakota was undertaken during the Great Depression with the aid of federal Public Works Administration (PWA) funds. The PWA supplied a $19,890 grant for the project, whose total cost was $50,891. Work occurred between December 1938 and June 1939.
(PWA Docket No. SD [W]1046)
Source notes
National Archives: Record Group 135: Public Works Administration; Projects Control Division; Entry 52: Indices to Non-Federal Projects; Report No. 5: Status of All Completed Non-Federal Allotted Projects, page 155.
Project originally submitted by Evan Kalish on December 8, 2014.
We welcome contributions of additional information on any New Deal project site.