- City:
- North Platte, NE
- Site Type:
- Infrastructure and Utilities, Roads, Bridges, and Tunnels
- New Deal Agencies:
- Public Works Funding, Public Works Administration (PWA)
- Started:
- 1938
- Completed:
- 1938
Description
A street paving project in North Platte, Nebraska was undertaken with the assistance of federal Public Works Administration (PWA) funds. The PWA supplied a $29,123 grant for the project, whose total cost was $56,171.
PWA Docket No. [W]1313
Source notes
National Archives: Record Group 135: Public Works Administration; Projects Control Division; Entry 52: Indices to Non-Federal Projects; Report No. 5: Status of All Completed Non-Federal Allotted Projects, page 149.Site originally submitted by Evan Kalish on May 3, 2015.