Description
(10.28 Acres) Plymouth Avenue and Lobos Street. Graded 6,000 cubic yards, built concrete and rubble walls and paths, gutters, tennis courts, water system, landscaped 9 acres. A large convenience station was built which is to become a part of a club house that is planned for the future.–Healy, p. 64.
Source notes
Healy, Clyde E. San Francisco Improved: Report of Clyde E. Healy, Assistant City Engineer - City of San Francisco and Coordinator of W.P.A. Projects, Period October 10, 1935 to August 31, 1939. San Francisco : [s.n.]., 1939. United States. Work Projects Administration (Calif.) Report on Progress of the Works Program in San Francisco. January, 1938. Works Progress Administration / William Mooser, Jr., branch manager. [San Francisco? 1938]Site Details
Total Cost |
---|
$189,642.00 |
Contribute to this Site
We welcome contributions of additional information on any New Deal site.
Submit More Information or Photographs for this New Deal Site
Join the Conversation