The WPA first demolished the original school, which had been condemned as a fire hazard. New buildings included a seven classroom frame and stucco building, with and auditorium and library, ground improvements, and the conversion of an older building into a cafeteria.
Source notes
Connolly, Donald H. and G. I. Farman. Report of Accomplishments of the Operations Division. Works Progress Administration: Southern California. January 1, 1939.Site Details
Federal Cost | Total Cost |
---|---|
$62,986.00 | $83,384.00 |