- City:
- McKeesport, PA
- Site Type:
- Infrastructure and Utilities, Roads, Bridges, and Tunnels, Sanitation and Water Disposal, Sidewalks and Stairs
- New Deal Agencies:
- Public Works Administration (PWA), Public Works Funding
- Started:
- 1936
- Completed:
- 1938
Description
A substantial infrastructure development project was undertaken in downtown McKeesport as part of a New Deal project, sponsored by the Public Works Administration (PWA). According to the Pittsburgh Press the project involved: “Raising and paving of Fifth Avenue and adjacent streets and alleys, approximately 3380 feet long, grant of $388,350, total estimated cost $863,000. The project provides also for elevating a number of houses to conform to the new street grade line.”
The eventual total cost was listed as $849,659, and the project also involved sewer construction.
PWA Docket No. PA [W]1504
Source notes
National Archives: Record Group 135: Public Works Administration; Projects Control Division; Entry 52: Indices to Non-Federal Projects; Report No. 5: Status of All Completed Non-Federal Allotted Projects, page 34.
The Pittsburgh Press: July 29, 1936 (pg. 2)
https://www.newspapers.com/newspage/147053621/ (accessed Mar. 2018)
Site originally submitted by Evan Kalish on March 17, 2018.
Contribute to this Site
We welcome contributions of additional information on any New Deal site.
Submit More Information or Photographs for this New Deal Site
Join the Conversation