Newcastle was approved 2/28/1934 for construction of a sanitation disposal plant by the PWA. The project was awarded 8/30/1934 and work started 12/10/1934. The project was funded with a loan of $24,500, grant of $9,322, for a total expenditure of $33,444 when the project was completed 6/13/1935. The location of the project is presently unknown to Living New Deal.