Description
The Works Progress Administration (W.P.A.) conducted a development / improvement program at what is now known Claremont Municipal Airport.
- “Develop and improve municipal airport”
Official Project Number: 165‐1‐13‐18
Total project cost: $118,235.00
Sponsor: War Department - “Improve airport”
Official Project Number: 265‐1‐13‐13
Total project cost: $101,719.00
Sponsor: Town Board of Selectmen - “Develop airport”
Official Project Number: 265‐1‐13‐2
Total project cost: $93,979.00
Sponsor: Town Board of Selectmen
Source notes
Nationwide Context, Inventory, and Heritage Assessment of Works Progress Administration and Civilian Conservation Corps Resources on Department of Defense Installations, July 2009 (page C-112).
Project originally submitted by Evan Kalish on February 6, 2018.
We welcome contributions of additional information on any New Deal project site.
SUBMIT MORE INFORMATION OR PHOTOGRAPHS FOR THIS SITE