Description
“This P.W.A. allotment made it possible for the Quartermaster Corps of the Army to erect 12 field officers’ quarters of the type illustrated on this page. Each building provides heater, fuel, and storerooms, and a laundry in the basement; a living room, sun porch, dining room, kitchen, pantry, garage, and maid’s room on the first floor; and three bedrooms, two baths, and a dressing room on the second floor. They are frame buildings with exterior walls of native quarry stone. They were completed in February 1936 and the P.W.A. allotment, which involved other buildings at the post, was $688,707.”
Source notes
C.W. Short and R. Stanley-Brown. "Public Buildings: A Survey of Architecture of Projects Constructed by Federal and Other Governmental Bodies Between the Years 1933 and 1939 with the Assistance of the Public Works Administration." (1939).