• City Hall (former) - Easton PA
    Architect John Reilly designed plans to rebuild the Easton City Hall, March 7, 1933, following damage by fire in December 1932. City Council approved application to Civil Works Administration December 1933. Construction began in January 1934. Work on CWA funded projects was suspended in late February, but resumed on the city hall project April 3, 1934 when the men were called back to work. Work was temporarily halted, and again resumed in May when the city hall project was ordered to proceed at 100 percent capacity. By August, progress was reported behind schedule because only a small amount of funds...