• Elementary School - Ripley MS
    Public Works Administration (PWA) project 1280 provided a grant of $16,411 for construction of a grammar school. Architect E. L. Malvaney designed the 1-story brick school. The Daily Clarion-Ledger reported both the high school and the elementary school were constructed with this grant. The project was approved 8/10/1938, construction started 11/21/1938, and the project was completed 10/28/1939 for a total of $35,074. WPA provided an additional $3,640 for the grammar school to add landscaping, playground equipment, and sidewalks in February 1940.
  • Fraternity and Sorority Houses (former) - University MS
    The University of Mississippi made application to the Public Works Administration September 7, 1935 for grants to help construct five fraternity houses and two sorority houses. Funds in the amount of $2,000 for each structure were requested from PWA, and the university would fund the remaining $3,000 per building.The university requested $45,454 for fraternity and sorority houses according to a separate Clarion-Ledger article.Architects began drawing up plans for the first of ten sorority and fraternity houses, and the establishment of “fraternity row” after being notified funds had been obtained reported architect E. L. Malvaney. Work was ordered to begin on...
  • Gymnasium - Cleveland MS
    The gymnasium was constructed 1938-1939 as Public Works Administration project W1232. Architect E. L. Malvaney designed the gymnasium with a seating capacity of 1000, offices for athletic officials, dressing rooms, and a band hall on the second floor. It was converted to use as the Girls' gymnasium when a new one was constructed 1946 for boys. A grant of $16,930 was provided toward the total cost of $37,827. The project was approved 6/22/38, started 9/33/38, and completed 4/17/39. The building was demolished July 2019.
  • Gymnasium (former) - Como MS
    The Como gymnasium, recreation hall, two classrooms, and kitchen were PWA project W1256, approved June 22, 1938. The estimated cost was $22,727 and a $10,227 grant was awarded toward the project. Construction began August 25, 1938, and was completed February 2, 1939, at a final cost of $22,887. Architect was Edgar Lucien Malvaney.
  • H. M. Nailor School Complex (former) - Cleveland MS
    The Nailor High School was initially known as the Cleveland Consolidated School for African American students. It was designed by architect E. L. Malvaney and approved as WPA No. 50,022 in the fall of 1940. The monolithic concrete building contained two wings of classrooms connected by an auditorium seating 400, with a proposed cost of $63,000. WPA approved $25,394 toward the cost of the new school. "Nailor's poured concrete construction and Art Moderne style is almost unique for black schools of the same period and would have made it one of the finest African American school buildings of its time"...
  • High School - Hazlehurst MS
    The former Hazlehurst grammar school was PWA project W1077. The project was approved 9/25/1935 and completed 11/10/1936 for a total cost of $50,004. PWA supplied a $27,500 loan and a $22,457 grant. The school was enlarged in 1947, and currently serves as the high school. Work on clearing the lot began January 1936. Contractor was J. R. Flint and architect was E. L. Malvaney.
  • High School - Ruleville MS
    Ruleville's 1936 high school was completed as W1006 of the PWA program, with a $33,000 loan and $26,999 grant. The 2-story brick and tile school was approved September 25, 1935, and construction began in December. Architect E. L. Malvaney designed the 160x53 foot building with an 80x60 foot auditorium. It contained 18 classrooms. O. B. Douglass Construction Company received the bid for construction, Paine Heating and Tile plumbing and heating, and Stuart C. Irby Company did the electric wiring. The school was completed in August 1936. A grandstand with seating capacity of 300 and fence around the athletic grounds was finished...
  • School - Kokomo MS
    The Kokomo Consolidated School building was approved as Mississippi project 8723 in 1934. Construction began in October and was completed June 23, 1935 at a total cost of $23,034. E. L. Malvaney was the architect of the Colonial Revival school, which was constructed by Currie and Corley builders and contractors.
  • School - New Albany MS
    The 1936 high school was designed by E. L. Malvaney, and constructed by Walter L. Perry Construction Company. Mississippi project W1034 provided a $40,909 grant and the city funded the remainder of the total cost of $92,437. Construction began March 25, 1936 and was completed January 20, 1937. The school was demolished at some point, but the concrete bas relief panels--found on many of E. L. Malvaney's Mississippi schools, were salvaged and erected at the back of the new school.
  • Union County Jail - New Albany MS
    A new county jail and improvements to the existing county courthouse were approved as PWA project 1272 July 23, 1938. E. L. Malvaney was architect for the two-story concrete Art Deco jail. Construction began 10/10/1938 and was completed 3/29/1939. PWA supplied a grant of $20,454 toward total cost of $45,577. Bonds were issued in the amount of $25,000 to contribute toward the cost of new jail construction and repair of the courthouse.
  • Vaiden High School (former) - Vaiden MS
    The Art Moderne school was completed in 1943 as W. P. A. Project No. 7233. Work began in 1941 but was stopped due to lack of money resulting from the war. WPA workers mixed concrete on site, and carried it in wheelbarrows to construct the poured monolithic concrete two and a half story U-plan school. The auditorium was restored in 2008-2009 for use as a community center.
  • War Memorial Building - Jackson MS
    The Art Moderne building was Public Works Administration (PWA) Project Miss. 1279. Along with principal architect E. L. Malvaney, there were 8 architects, the builder/contractor, foundation contractor, and a sculptor who worked on the building.
  • Wayne County Courthouse - Waynesboro MS
    The 1936 Wayne County Courthouse was completed with a Public Works Administration grant (W1041) of $45,000 towards the $100,000 building. E. L. Malvaney designed the 51 x 110 foot Art Deco style building constructed of gray brick with stone trim and steel sash. I. C. Garbor and Son were the construction company. The top floor of the 4-story building contained a "modern, escape-proof jail" ("New Wayne County Courthouse Awaits Dedication") and the interior was trimmed with red gum. Heating and plumbing was done by S. S. Richard Heating and Plumbing, and electric by Short Electric Company. The courtrooms contained 300...