• City Improvements: water mains, sewers, streets, gutters, curbs - Lodi CA
    The city of Lodi and the WPA constructed and installed 15.8 miles of water mains, 101 fire hydrants, 8.8 miles of sanitary sewers and manholes, 12,230 feet of storm drains and manholes, catch basins. Almost every street and alley has been graded and oiled, 21.5 miles of curbs and gutters constructed, sludge disposal plant decanter constructed, Lockeford Street and School Street work finished.
  • Lodi Lake Improvements for Recreation - Lodi CA
    The WPA added 12 acres of parkland to the existing park at Lodi Lake, and a bridge built to link the two parcels of land. Also with the help of WPA funds and 26 men over 20 months, the city constructed dressing rooms, an office building, grading and oil surfacing of the park roads, a parking lot, the installation of riprap, dredging, painting of boats and benches and tables.