North Metropolitan Relief Sewer - Everett MA The Federal Emergency Administration of Public Works (a.k.a. Public Works Administration, or PWA) sponsored construction of the North Metropolitan Relief Sewer.
Section 105: "This section is located in Medford and Everett and embraces the construction of about 6500 feet of sewer varying in size from 8'6" to 10'6" and including an inverted siphon about 350 feet long in tunnel under the Malden River, two tunnels at railroad crossings, a tunnel under the Fellsway, and a tunnel under the Revere Beach Parkway. Bids were opened on this section on December 8, 1938. The contract was awarded by the Metropolitan District Commission on December...