• Street Improvements - Hernando MS
    PWA project 1200 for paving in Hernando was for $16,000 loan and $13,090 grant approved 11/17/1936. Construction began 4/5/1937 and was completed 6/10/1937 for a total cost of $29,571. The work included paving the street around the courthouse square and surfacing eight lateral streets in the town. Contract was awarded to Bowyer & Johnson for $25,037.