• Everett Public Library - Everett WA
    Everett, Washington's main library was constructed between 1933 and 1934 with the assistance of federal Public Works Administration (PWA) funds. The PWA provided a grant of $23,600; the final cost of the project was $108,112.
  • Everett Sewer System - Everett WA
    "The project began in October of 1938 and ran 6.5 miles of sewer pipes through Everett. At a cost of $110,839 the project improved the sewer system throughout Everett at no cost to residents." (https://depts.washington.edu)
  • Snohomish County Airport (Paine Field) - Everett WA
    "In 1937 WPA funds were granted to Snohomish County Airport. $225,000 was granted by the War Department who oversaw all airport construction and renovation between 1933 and 1938."
  • Street Improvements - Everett WA
    A WPA press release from Jan. 1938 reported that city streets in Everett, Washington were to be improved with a WPA grant of $38,024.