• Long Pine School - Long Pine NE
    The Long Pine School project was begun and left unfinished by the Civil Works Administration (CWA) and the Emergency Relief Agency (ERA). As a result, the school’s roof leaked and the heat did not work. Because the school district’s finances were not robust enough to pay to finish the project itself, the district proposed to finish the project with the Works Progress Administration (WPA). Included in the work was a renovation of all the units within the building including painting all surfaces, sanding and varnishing all floors, doors, desks and furniture, the excavation and cementing of the basement of the...